ProjectLibre - Sobreasignación de recursos

ProjectLibre - Sobreasignación de recursos

Managing Resource Allocation in Project Management

Overview of Resource Management

  • The video discusses managing human and material resources within free project management tools, highlighting the process of assigning these resources to various project tasks.
  • It presents a completed project where resources have been assigned across all phases: requirements, analysis, and implementation.

Identifying Over-allocation

  • The next step after resource assignment is to check for over-allocation, which occurs when work exceeds the established hours (typically 8-9 hours).
  • Over-allocation can be reviewed using a histogram feature accessible via buttons on the screen. This tool helps visualize resource assignments effectively.

Analyzing Resource Assignments

  • Clicking on a specific human resource displays their task allocation histogram; green shaded areas indicate assigned tasks that should not exceed histogram limits. For example, Israel Fernández's allocations are compliant with this rule.
  • In contrast, Gerardo López shows over-allocation on specific days (March 22 and 25), as indicated by green areas exceeding histogram dimensions. This highlights the need for corrective action.

Resolving Over-allocation Issues

Method 1: Reassigning Tasks

  • To resolve over-allocation, one simple method is to double-click on an over-assigned task and reassign it to another resource by removing the original assignment. This adjustment resolves conflicts effectively.

Method 2: Linking Tasks

  • If tasks must be performed by the same specialized resource but cannot overlap in time, linking them ensures one starts after the other finishes automatically, thus avoiding over-allocation while maintaining necessary constraints.

Method 3: Adjusting Workload Percentage

  • When both tasks must start simultaneously but require adjustments due to workload constraints, modifying each task's percentage (e.g., from 100% to 50%) allows for balanced distribution without causing over-allocation issues while extending overall task duration accordingly.

Method 4: Task Division for Sequential Tasks

  • In cases where sequential tasks interfere with each other (like meetings or presentations), dividing a task creates space for overlapping activities without leading to over-allocation issues—demonstrated through practical examples in the video involving specific tasks assigned to resource A.
Video description

En este video aprenderemos como detectar la sobreasignación de reecursos en ProjectLibre así como cuatro técnicas para resolver este problema #projectlibre #projectmanagement #sobreasignacion