Introduction to PERT Diagrams

Overview of PERT Diagrams

  • PERT (Program Evaluation Review Technique) diagrams are tools for planning and controlling projects in a graphical manner.
  • They utilize probabilistic methods to estimate execution times for project activities, identifying critical activities that cannot be delayed.

Steps to Create a PERT Diagram

  • The process involves six steps:
  1. Order activities by occurrence.
  1. Establish expected times for each activity.
  1. Create arrow diagrams.
  1. Calculate the project's expected time.
  1. Determine slack for each activity.
  1. Calculate the critical path.

Detailed Explanation of Activity Ordering

Activity Sequencing

  • Activities must be organized sequentially based on their occurrence within the project timeline.
  • Three time estimates are used: optimistic time (minimum duration), average time (normal conditions), and pessimistic time (maximum duration).

Establishing Expected Times

Calculating Expected Time

  • To calculate expected time, use the formula: textOptimistic + 4 times textAverage + textPessimistic / 6 .
  • This method is repeated for all activities to derive their respective expected times.

Creating the Arrow Diagram

Rules for Diagramming

  • Each node represents an activity; only one node per activity is allowed.
  • An initial and final node must be established to define the network's boundaries.

Calculating Project Time and Critical Path

Time Calculation Methodology

  • Use a spreadsheet to track early start times, which equals the earliest finish of preceding activities plus their durations.
  • Late start times are calculated by subtracting durations from late finish times, determining slack as differences between early and late starts or finishes.

Variance and Standard Deviation in Project Management

Understanding Variance

  • Variance is calculated as (textPessimistic - textOptimistic)^2 / 36 .
  • The standard deviation is derived from the square root of total variance across critical path activities.

Probability of Completing Projects on Time

Probability Calculation Process

  • To find completion probability within a specific timeframe (e.g., 25 weeks), use normal distribution tables after calculating area under the curve using X = (textTarget Time - textExpected Time) / textStandard Deviation .

Conclusion and Resources

Final Thoughts

  • The tutorial emphasizes using PERT diagrams as an effective method for project management calculations, encouraging viewers to explore additional resources available online through various platforms like Facebook, Twitter, YouTube, and their website.

Turn any video into a summary like this

YouTube links, meetings, lectures. With transcripts, search, and chat.

Video description

En este tutorial se explicará cómo planificar un proyecto utilizando la técnica PERT, adicionalmente se encontrará el ejemplo utilizado en vídeo visitando la página Utilidades de Gestión (https://utilidadesdegestion.com) revisando el artículo "Diagrama PERT".