Ayuda para parcial 4

Ayuda para parcial 4

Introduction to Filling Out the Exam File

Overview of the Process

  • The speaker greets the audience and introduces a brief explanation on how to fill out a file for an upcoming partial exam.
  • The first exercise involves calculating Net Present Value (NPV), with two alternatives named Aurora and Boreal.

Steps for Completing the Exercise

  • Identify the alternatives: Aurora and Boreal, followed by noting down the discount rate of 18% and a useful life of 20 years.
  • The initial investment is stated as $85,000, which is recorded in the designated area.

Details on Operational Costs

Annual Savings and Expenses

  • An annual savings from materials and labor is noted at $26,000; no currency symbols are required when entering this data.
  • Operating expenses for year one are $9,500, decreasing by $1,000 each subsequent year.

Maintenance Costs

  • Maintenance occurs every six years at a cost of $5,000; scheduled for years 6, 12, and 18.
  • There is no salvage value mentioned for this alternative.

Transition to Alternative Boreal

Key Financial Figures

  • For Boreal, the initial cost is set at $68,000 with annual savings from labor/material amounting to $17,000 that increases by $1,000 each year.
  • Operating expenses are specified but not detailed in this section; maintenance occurs every five years costing $6,000.

Salvage Value Consideration

  • A salvage value of an unspecified amount exists but will not be included if it coincides with the end of its useful life.

Summary of NPV Calculations

Finalizing Results

  • The calculated NPV results need to be transferred accurately into the exam format.
  • The chosen machine based on calculations is Aurora; explanations will accompany each choice made during analysis.

Introduction to Cost Annual Equivalent Analysis

New Alternatives Introduced

  • The second exercise focuses on Cost Annual Uniform Equivalent (CAUE), introducing machines named Fénix and Centauro.

Investment Details

  • Fénix has an initial investment of $480,000 with income projections outlined alongside energy costs totaling $65,000.

Maintenance Schedule for Fénix

Scheduled Maintenance Costs

  • Maintenance occurs every four years at a cost of $18,000; applicable in years 4 and 8 only due to project lifespan constraints.

Overview of Centauro's Financial Metrics

Income and Expenses Breakdown

  • Centauro costs $180,000 with projected income at $215,000 while energy costs reach up to $90,000.

Maintenance Frequency

  • Scheduled maintenance happens every two years costing approximately $8,500; applicable in years 2 through 8 excluding final year considerations.

Conclusion

Submission Process

  • After completing all exercises correctly according to guidelines provided throughout this session , students can submit their answers online where confirmation will follow via email.