Visita Virtual de 360° a la Subestación Aniversario de Edenor

Visita Virtual de 360° a la Subestación Aniversario de Edenor

Virtual Tour of Subestación Aniversario

Introduction to the Visit

  • The visit will explore the Subestación Aniversario with eight stops, featuring videos by Engineer Marcelo Fabbro, who oversees operations and substation supervision.
  • The activity lasts approximately one hour and is self-guided; questions are encouraged throughout the tour rather than at the end.
  • Participants can access a link for further exploration of this virtual experience, allowing repeated visits and use in educational settings.

Overview of Subestación Aniversario

  • Located in Vicente López, just 600 meters from Río de la Plata and 800 meters from Avenida General Paz, designed to blend with its environment resembling a ship.
  • This year’s virtual experience allows broader access; over 1,000 people have participated across multiple presentations.

Safety Protocols

  • Normally, visitors must wear helmets and protective shoes when entering the substation; however, these requirements are waived for the virtual tour.

Understanding Electricity

Importance of Electricity

  • Electricity is essential for daily activities such as lighting, refrigeration, charging devices, and internet usage.
  • Proper generation and distribution of electricity are crucial for homes and businesses; substations play a key role in this process.

Role of Substations

  • Substations transform high-voltage electricity into lower voltages suitable for distribution to consumers.

Features of Subestación Aniversario

Construction Details

  • Inaugurated in 2017 to commemorate Edenor's 25th anniversary; built on a uniquely narrow plot measuring 125m long by 25m wide.
  • The construction faced challenges due to space constraints requiring innovative engineering solutions.

Investment Impact

  • The investment totaled $12.6 million benefiting around 75,000 customers in Vicente López and northern Buenos Aires.

Types of Substations

Classification by Functionality

  • There are elevating substations near power plants that increase voltage for transport and reducing substations that decrease voltage for safe distribution.

Technological Advancements

  • New technologies allow compact designs occupying only 4% to 8% of conventional sizes while maintaining operational efficiency.

Control Room Insights

Control Room Overview

  • All substations include control rooms where electrical components are monitored; this room houses telecontrol systems ensuring operational safety.

Auxiliary Services Explained

  • Auxiliary services provide necessary energy for equipment operation within the substation including lighting and ventilation systems.

Maneuvering Area Operations

Maneuvering Area Description

  • The maneuvering area contains outdoor equipment operating at two voltage levels: primary (132 kV), linked to transmission systems, and secondary (13.2 kV), connected to distribution networks.

High Voltage Equipment

High Voltage Components

  • Equipment includes high-voltage disconnect switches which separate parts electrically providing visible cuts during maintenance operations.

Conclusion on Equipment Functionality

  • Interruptors monitor continuously ensuring rapid response during faults generating alarms locally or sending alerts back to control centers.

Overview of Substation Platforms

Structure and Functionality

  • The platforms are constructed from concrete to support transformers and manage oil spills during emergencies.
  • They include a flame wall, which must exceed 2 meters in height to prevent fire spread between transformers, allowing firefighters to cool adjacent units safely.
  • The functionality of all components within the substation is critical for operational safety and efficiency.

Mixed-Type Substations

Transmission and Distribution

  • This mixed-type substation facilitates both transmission from other substations (Edison and Nuevo Puerto) and distribution through its transformers.
  • Transformers are standardized at 80 MVA, with configurations allowing simultaneous transmission and power extraction.

Transformer Configuration

Technical Specifications

  • Each transformer has a primary and secondary output, providing two outputs of 40 MVA each through medium voltage cables.
  • These transformers do not utilize tertiary windings; however, they are used in higher voltage applications (120 kV).

Control Room Insights

Energy Distribution Management

  • The control room houses maneuvering panels that distribute energy among nearby transformation centers using four sections with eight outgoing cables each.
  • An automatic load transfer system ensures continuity during failures by closing couplers under specific conditions.

Safety Features in Equipment

Protection Mechanisms

  • Increased safety measures protect active parts from arc flash incidents, minimizing risks for operators and surrounding equipment.
  • Primary distribution cells feature removable switches for quick maintenance without compromising operational flexibility.

Medium Voltage Switches

Operational Characteristics

  • Medium voltage switches use vacuum-sealed contacts to interrupt nominal currents or short circuits effectively while operating up to 17.5 kV.
  • Interchangeability allows rapid replacement of faulty switches with similar models.

Synchronization Queries

System Integration

  • Normal operations involve synchronization within the same subsystem for effective coupling; this is managed by dispatch based on demand conditions.

Relay Protection Systems

Advanced Monitoring

  • Modern relays function as small computers monitoring outputs; they coordinate protection mechanisms across multiple levels within the system.

Capacitor Banks

Reactive Power Management

  • Capacitor banks installed at the substation regulate reactive power flow between sources and loads while ensuring personnel safety against direct contact.

Site Selection Challenges

Practical Considerations

  • Selecting sites for new substations involves balancing theoretical planning against real-world constraints like land availability or existing structures.

Future Expansion Plans

Anticipated Developments

  • Edenor plans future substations including José y Sepas, Libertad in Merlo, San Juan near Campos de Mayo, aiming to meet increasing demand efficiently.

Turn any video into a summary like this

YouTube links, meetings, lectures. With transcripts, search, and chat.

Video description

El día 1 de diciembre de 2020 se realizó una visita virtual a la Subestación Aniversario, ubicada en Vicente López. La subestación transforma la tensión de 132 kV a 13,2 kV; se alimenta mediante un cable de 132 kV que interconecta las subestaciones Edison y Nuevo puerto. Cuenta con dos transformadores de 80 MVA, que alimentan un tablero de celdas de distribución de 13,2 kV formado por cuatro secciones de nueve salidas de cables de 13,2kV cada una. La obra, que incluye 500m² de construcciones subterráneas, integra las inversiones comprometidas por la empresa Edenor para su plan quinquenal 2017-2021. Enlace para realizar una visita virtual: http://bit.ly/Visita360SEAniversario