ProjectLibre - Relaciones de actividades e hitos

ProjectLibre - Relaciones de actividades e hitos

Establishing Linear Relationships in Project Management

Introduction to Linear Relationships

  • The video begins by discussing how to establish linear relationships between activities in project management, specifically using predecessor columns. For example, Activity 4 is preceded by Activity 3, and so on.

Simplifying Relationship Establishment

  • A simpler method for establishing these relationships is introduced: selecting activities and clicking on the "Task" menu to use the "Link Automatically" option. This feature is particularly useful for managing long task lists.

Types of Dependencies

  • The most common relationship type discussed is Finish To Start (FS), where one activity must finish before another starts (e.g., Activity 1.1 must finish before Activity 1.2 can start). This dependency can be viewed in the predecessors tab of the software.
  • Other types of dependencies are also mentioned:
  • Finish to Finish (FF): Both activities must finish simultaneously.
  • Start to Start (SS): Activities begin at the same time. An example is provided showing how this affects scheduling visually in a Gantt chart.

Modifying Dependencies with Lag

  • It’s explained that while FS is a default relationship, it can be modified by adding lag time (delays) between tasks, such as delaying Activity 2.1's start by two days after its predecessor finishes. Negative lag can also be applied, allowing an activity to start before its predecessor finishes by one day. This adjustment updates the Gantt chart accordingly.

Capturing Milestones in Project Schedules

Definition and Importance of Milestones

  • A milestone is defined as an activity with zero duration that signifies significant events within a project timeline, such as completing work packages or phases. Understanding milestones helps track progress effectively throughout a project lifecycle.

Creating Milestones in Software

  • To add a milestone, users right-click and select "New," then set its duration to zero days; this changes its graphical representation to a diamond shape on the schedule diagram, indicating it’s a milestone event linked with relevant activities like Work Package 1 completion.

Linking Additional Milestones

  • Similar steps are followed for creating additional milestones for other work packages (e.g., Work Package 2), reinforcing that setting their duration to zero automatically designates them as milestones within the project management software interface. This visual cue aids clarity in tracking project progress and deadlines effectively.
Video description

En este video se muestra las diferentes formas en que se pueden relacionar dos actividades y se crean actividades como hitos de proyecto #projectlibre #hitos #projectmanagement