Crónica del BYPASS más VELOZ del PERÚ | ¡SOLO 7 MESES de construcción!
Overview of the Viaduct Las Torres Construction
Introduction to the Project
- The Viaduct Las Torres was constructed in just 7 months and is crucial for expanding the Ramiro Priale highway, connecting older sections from the 1980s with new extensions leading to the Morón bridge.
Initial Planning and Site Conditions
- The intersection area with Avenida Las Torres was identified for a future underpass by the Metropolitan Municipality of Lima, which had already included this project in its plans as early as January 28, 2025.
- Initially, the site was an illegal dumping ground for trucks and heavy machinery, lacking any connection between old and new road segments due to previous infrastructure hindrances.
Groundbreaking and Early Construction
- Official construction began on May 31, 2025, marked by a ceremonial laying of the first stone; initial excavation work commenced shortly after on June 5.
- By June 27, traffic diversions were implemented as foundational work progressed on the bypass.
Foundation Work Progress
- Observations showed significant advancements in foundation work including steel installation and concrete pouring; many foundations were nearly complete by July 19.
Column Construction
- While foundations were being laid out, prefabricated columns were simultaneously constructed for assembly in August.
Structural Developments
Assembly of Columns and Head Structures
- By August 16, some prefabricated columns had been assembled onto their foundations, expediting construction timelines significantly.
- By September 20, prefabricated head structures supporting future beams and slabs were installed alongside progress on abutments from both east and west access points.
Installation of Beams and Slabs
Advancements in Superstructure
- On October 9, installation of initial beams began while slab sections were also under construction; partial resurfacing towards Lima commenced concurrently.
Continued Structural Assembly
- As of October 25, ongoing assembly of prefabricated beams continued along with concrete pouring for slabs; earthworks started for ramp constructions.
Final Stages Before Completion
Finishing Touches
- By October 30, final beam assemblies were nearing completion alongside extensive concrete pouring across all slabs.
- On November 10, structural form became evident with final slab pours underway despite minor incidents involving local police.
Completion Milestones
Structural Readiness
- By November 28, structural integrity was achieved with visible completion of major components.
Access Infrastructure Development
- December saw New Jersey walls being formed while access ramps underwent compaction processes.
Operational Readiness
Final Preparations
- As of December 30th's last aerial survey that year revealed near-completion status with asphalt application ongoing at key access points.
Opening Phases
- A trial run initiated on January 9th allowed two lanes towards Chosica to operate while opposing directions awaited clearance from Carapongo interference removal.
Full Operation Launch
- Interference issues resolved by January's end led to earthworks commencing at eastern access ramps; full operational capacity achieved by March 4th when dual-direction traffic opened up.
Current Status
- The viaduct is now fully functional with LED lighting installations pending alongside minor surface works expected to conclude shortly.