Estimar los costos y determinar presupuestos de un proyecto

Estimar los costos y determinar presupuestos de un proyecto

Explanation of Activity for Cost Management Course

Overview of Steps in Cost Estimation

  • The activity corresponds to Step 3 of the project cost management course, focusing on estimating costs and determining the budget.
  • Estimating costs involves identifying all elements that incur expenses within the project, such as materials, human resources, services, equipment, systems, risks, and quality.
  • Outputs from cost estimation will be presented using Microsoft Project or Libre Project with a complete schedule of activities established in Step 2.

Quality Management Plan

  • A matrix will be constructed for the quality management plan detailing activities and resources necessary to achieve established quality objectives.
  • The quality management plan must include standards and objectives chosen in Step 2 along with roles and responsibilities for ensuring project quality.
  • It is essential to identify deliverables subject to quality review and outline planned quality control activities.

Documenting Project Requirements

  • Costs associated with essential resources required for each work package must be estimated based on previously described activities.
  • A format for documenting resource requirements will help estimate costs related to human resources distinct from those responsible for quality assurance.

Risk Management Costs

  • Risks identified in Step 2 should be documented in a risk register where their causes, probabilities, impacts, and mitigation costs are estimated.
  • Environmental factors influencing cost estimation need investigation; this includes market conditions and organizational process assets.

Tools and Techniques for Cost Estimation

  • After constructing inputs like the quality management plan and risk register, these should be uploaded into Microsoft Project or Libre Project for analysis.
  • An analysis of reserves is crucial; contingency provisions must be included in the budget to account for identified risks.

Finalizing Cost Estimates

  • A screenshot of the tool showing all phases, activities, and estimated costs will serve as documentation of total budget estimates.
  • Updates may need to be made regarding risks as they evolve throughout different project phases after initial cost estimations are completed.

Determining Budget

  • The budget determination involves summing up estimated costs across individual activities or work packages outlined during project initiation.
  • A resource acquisition plan should also detail responsibilities related to managing these resources effectively throughout the project's lifecycle.

Business Case Considerations

  • Identifying expected benefits is important; this includes calculating present value metrics associated with anticipated outcomes from the project.

Updating Risk Register

  • Finally , any new risks identified during budgeting must also be updated in the risk register to ensure comprehensive tracking throughout the project's duration.