Mod-01 Lec-23 Drilling from Platforms

Mod-01 Lec-23 Drilling from Platforms

Introduction to Drilling from Fixed Platforms

In this section, the lecturer introduces drilling from fixed platforms and discusses different types of platforms used for drilling.

Types of Platforms

  • Jack-up Rigs: These are bases that can be raised or lowered using legs.
  • Submersibles: These have two hulls, one above the water level and the other on the seabed. They were used in shallow waters in the 1940s but are not commonly used nowadays.
  • Jackets: These are fixed coastal structures that serve as guides for pipes.

Submersibles and Shallow Water Drilling

This section provides more information about submersibles and their use in shallow water drilling.

  • Submersibles have two hulls, with one above the water level and the other on the seabed.
  • They were used in shallow waters with depths around 12 meters.
  • While submersibles are not widely used today, they can still be found in marshy areas.

Jackets Platforms

This section focuses on jackets platforms and their role in drilling operations.

  • Jackets are fixed coastal structures that serve as guides for pipes.
  • The main purpose of drilling is to set up a conductor pipe, which transports oil from the well below to the platform.
  • Conductor pipes extend from above the waterline to slightly below the seabed.

Functions of Conductor Pipe

This section explains the functions of a conductor pipe in drilling operations.

  • The primary function of a conductor pipe is to guide drill pipes and prevent collapse of the borehole.
  • It serves as an important pipeline for transporting oil from the well to the platform.
  • The conductor pipe extends from above the waterline to slightly below the seabed.

Process of Drilling

This section provides an overview of the drilling process and its components.

  • The drilling process is similar whether it is conducted from a fixed platform or a floating platform.
  • The drill string consists of a drill bit, drill collar, and drill pipe.
  • The drill string is suspended from the derrick using a swivel and rotates with the help of a rotary table.

Components of Drill String

This section discusses the components of a drill string used in drilling operations.

  • The drill string consists of a drill bit, drill collar, and drill pipe.
  • Mud circulation is facilitated through hollow sections of the pipe.
  • Drill collars are added to increase vertical pressure on the drill bit if needed.

Rotary Table and Kelly

This section explains the role of the rotary table and Kelly in drilling operations.

  • The rotary table provides torque for rotating the entire drill string.
  • It has a square hole for inserting the Kelly, which is a square piece of rod.
  • The weight of the drill string provides vertical pressure on the drill bit.

Applying Vertical Pressure and Rotary Torque

This section discusses how vertical pressure and rotary torque are applied during drilling.

  • Vertical pressure on the drill bit is achieved by adding weight to the drill string.
  • Additional weights can be added by using more collars or attaching weights to achieve proper downward force.
  • Rotary torque is provided by rotating the rotary table using the Kelly as a connection point.

Role of Rotary Table in Providing Torque

This section highlights how torque is provided by the rotary table in drilling operations.

  • The rotary table has a square hole for the Kelly, which allows for a secure connection.
  • The square hole ensures there is no slippage during rotation, providing effective torque transfer.
  • As the rotary table rotates, the entire drill string moves downward, deepening the borehole.

These notes provide an overview of drilling from fixed platforms and cover important aspects such as platform types, conductor pipes, drill strings, and the role of various components in drilling operations.

Drill String and Draw Works

This section explains the concept of the drill string and draw works in drilling operations.

Drill String and Wire Ropes

  • The drill string is connected to the draw works using wire ropes.
  • As one length of drill pipe goes down, the entire drill string is hoisted up.

Connection with Kelly

  • The Kelly, a square piece of rod, is jointed to the top of the drill pipe.
  • The joint is opened up to remove the Kelly and connect another section of drill pipe.

Continuous Drilling Process

  • Additional sections of drill pipe are added to the top of the existing drill string.
  • The drilling process continues as more sections are added to the Kelley additional drill pipe.

Drill Bit and Casing

This section discusses the variations in drill bits and the use of casings in drilling operations.

Variations in Drill Bits

  • Different types of drill bits are used for drilling through hard or soft soil.
  • When a drill bit gets worn out, it needs to be replaced with a new one.

Casings

  • Casings are used to stabilize the borehole and prevent collapse.
  • Casings are suspended from a wellhead assembly and inserted into progressively narrowing holes.

Inserting Multiple Casings

This section explains how multiple casings are inserted into progressively narrowing boreholes.

Inserting Casing Strings

  • Multiple casings are screwed together to form a string from seabed to platform top.
  • Each casing is inserted inside the previous casing as depth increases.

Borehole Diameter Reduction

  • As drilling progresses, the diameter of the borehole decreases.
  • More casings need to be inserted to maintain stability and prevent collapse.

Borehole Collapse and Pressure Maintenance

This section discusses the issue of borehole collapse and the importance of maintaining pressure in drilling operations.

Borehole Collapse

  • Borehole collapse occurs when mud blocks the hole, causing it to flatten.
  • If borehole collapse happens, drilling must stop or the drill string needs to be turned.

Maintaining Borehole Pressure

  • Internal pressure inside the drill string is maintained to prevent collapse.
  • The combined pressures from hydrostatic head and earth pressure are countered by maintaining borehole pressure.

Pressure Encountered in Deeper Drilling

This section explains the increasing pressure encountered during deeper drilling operations.

Increasing Pressure

  • As drilling goes deeper into the reservoir, higher pressures are encountered.
  • Hydrostatic pressure and earth pressure contribute to the overall pressure on the borehole.

Preventing Collapse

  • To prevent collapse, internal pressure inside the drill string must be maintained.
  • Monitoring and maintaining borehole pressure is crucial for successful drilling operations.

New Section

This section discusses the importance of maintaining viscosity and fluid pressure in boreholes during drilling operations.

Maintaining Viscosity and Fluid Pressure

  • The amount of viscosity in the borehole needs to be maintained to ensure proper flow rate for the mud.
  • Certain chemicals are added to the mud to maintain required viscosity.
  • Maintaining fluid pressure in the borehole is crucial, especially as you go deeper into the earth where pressure increases.
  • Balancing external and internal pressures is essential to prevent collapse of the structure.

New Section

This section explains the need for balancing pressure in offshore structures and platforms.

Balancing Pressure

  • In deep water platforms, it is crucial to balance pressure between external forces and internal mud pressure.
  • Failure to balance pressure can lead to structural collapse.
  • Proper pressure balancing is necessary for boreholes, offshore structures, and large water depths.

New Section

This section describes the sequence of mud circulation during drilling operations.

Mud Circulation Sequence

  • Mud circulates through the Kelly drill string.
  • It flows out through a gap between the hole and drill string.
  • The mud comes to the surface through an annulus space between casing and string.
  • Mud pumps circulate the mud back into the system to maintain pressure and lubricate the bit.

New Section

This section discusses shale shakers and their role in separating rocks from mud during drilling operations.

Shale Shakers

  • Shale shakers separate broken pieces of rock (shale) from the mud.
  • Rocks and impurities are separated from the mud before it is driven down again.
  • Shale shakers are part of equipment on drill floors of platforms.

New Section

This section highlights the importance of topsides layout in offshore platform design.

Topsides Layout

  • Topsides refer to all the equipment and facilities on the deck of a platform.
  • Proper layout and arrangement of topsides are crucial for platform design.
  • Different types of platforms exist for exploratory drilling and production purposes.

New Section

This section explains the difference between exploratory drilling and production platforms.

Exploratory Drilling vs. Production Platforms

  • Exploratory drilling platforms are used for drilling operations to explore new areas.
  • Production platforms are designed for extracting oil from reservoirs.
  • Offshore engineering involves designing different types of platforms based on their specific purposes.

New Section

This section discusses floating platforms and the importance of topsides facility in platform design.

Floating Platforms and Topsides Facility

  • Floating platforms have important equipment located on their decks, known as topsides.
  • Topsides include pumps, mud tanks, and other necessary equipment.
  • Proper arrangement and design of topsides facility is crucial for platform design.

New Section

This section emphasizes the significance of deck design in offshore platform construction.

Deck Design

  • Offshore platforms are essentially deck-designed vessels rather than cargo-carrying ships.
  • The design process starts with the layout and arrangement of topside facilities.
  • Considerations include nature, size, weight, area, volume, and distribution of equipment within topside facilities.

New Section

This section discusses the underwater portion and topsides of a platform, as well as the importance of designing separate structures for each.

Designing Underwater Thrust and Topsides

  • The underwater portion supports the topsides and resists environmental loads from water such as waves and currents.
  • Two separate designs are required: one for the topsides (GA drawing) and one for the underwater thrust (structural design).
  • The topsides are supported by a deck called "deck topsides," while the underwater thrust is supported by "deck substructure."

New Section

This section highlights the differences between fixed platforms and floating platforms in terms of BOP location, motions, and maintenance.

BOP Location on Fixed Platforms

  • In fixed platforms, the BOP is located on the deck of the platform instead of on the seabed.
  • Fixed platforms have less motion and allow for easier maintenance of BOP equipment.
  • The blowout preventer assembly is situated on the seabed in fixed platforms.

New Section

This section explains the function of a blowout preventer (BOP) in regulating pressure inside a borehole to prevent blowouts.

Function of Blowout Preventer (BOP)

  • A blowout preventer is a set of valves used to regulate pressure inside a borehole.
  • It prevents blowouts caused by excessive pressure inside the borehole that cannot be maintained.
  • Blowouts can lead to disasters, including fires, as seen in incidents like the Gulf of Mexico blowout.

New Section

This section discusses remote operation guidelines for BOPs in floating platforms due to their location deep below sea surface.

Remote Operation of BOP in Floating Platforms

  • Floating platforms require remote operation of the BOP due to its location several hundred meters below the sea surface.
  • Guidelines are provided for loading equipment from the deck and remotely operating the BOP.

New Section

This section explains the sequence of mud circulation during drilling operations, including the role of various equipment.

Sequence of Mud Circulation

  • The sequence starts with a mud pump, followed by a swivel that allows mud to flow through the drill string.
  • Mud is circulated through drill collars, drill bit, and out through the annular space.
  • It then passes through a shale shaker to remove pieces of rocks, a desander to remove sand, and a degasser.
  • Finally, it goes back to the mud pump via a mud ditch. A reservoir is needed for collecting the mud.

New Section

This section provides an overview of additional equipment involved in drilling operations, such as blowout preventers.

Additional Equipment in Drilling Operations

  • Shale shakers are used to remove pieces of rocks from circulating mud.
  • Blowout preventers (BOPs) play a crucial role in preventing blowouts by regulating pressure inside boreholes.

The transcript does not provide further content beyond this point.

New Section

This section discusses the process of drilling and the use of a production Christmas tree. It also explains the challenges faced in drilling from fixed and floating platforms.

Drilling Process and Production Christmas Tree

  • After drilling, a production Christmas tree is used to replace the drill.
  • The production Christmas tree consists of valves that progressively decrease pressure in stages.
  • Valves sizes decrease as pressure decreases.

Drilling from Fixed Platforms

  • Drilling from fixed platforms is less challenging due to fewer motions and advantages of having the BOP assembly on deck.
  • A diagram shows drilling from a fixed platform with one casing and cement for stabilization.

Drilling from Floating Platforms

  • Drilling from floating platforms is more difficult due to BOP on seabed and intense remote operation.
  • Motions on marine riser pose a major technological challenge for naval architects.
  • Designing floating platforms with reduced motions, such as TFP concept, is important but not easy.

New Section

This section focuses on reducing riser motions in floating platforms through design considerations and heave compensating devices. It also mentions the study of platform stability, buoyancy considerations, and riser mechanics.

Reducing Riser Motions

  • Designing floating platforms with less motion is crucial to reduce riser motions.
  • Heave compensating devices are used to maintain tension on the drill string and prevent bending failure.
  • Riser mechanics study the coupled motions between platform and riser.

Vortex Shedding

  • Vibratory motions or shedding vibrations occur due to vortex shedding phenomenon.
  • Naval architects are concerned about these phenomena in relation to platform stability.

Platform Stability and Buoyancy Considerations

  • Stability and buoyancy considerations are important for both ships and platforms.
  • Mooring stiffness can be used as another method to restrict motions in floating platforms.

New Section

This section highlights the importance of studying platform motions and riser motions, which are interdependent. It also mentions the phenomenon of vortex shedding and its impact on risers.

Coupled Motions

  • Platform motions and riser motions are not independent but rather coupled.
  • The study of coupled motions is a complex area known as riser mechanics.

Vortex Shedding

  • Vortex shedding is a phenomenon that causes vibrations in risers.
  • Naval architects focus on understanding and mitigating vortex shedding effects.

New Section

This section emphasizes the importance of stability, buoyancy considerations, motion restriction, and mooring stiffness in floating platforms.

Stability and Buoyancy Considerations

  • Stability and buoyancy considerations are crucial for both ships and platforms.
  • These considerations involve factors such as GZ curve, GM, stability, and buoyancy.

Motion Restriction

  • Heave compensating devices help restrict motions in floating platforms.
  • Mooring stiffness is another method used to limit platform motions.

The transcript provided does not include timestamps for all sections.

New Section

This section discusses the importance of moorings in floating platforms and their contribution to platform design.

Moorings and Platform Design

  • Restricting motion on the riser and platform is crucial for floating platforms.
  • Moorings are a significant part of the platform, requiring storage within the platform itself.
  • Platform designs revolve around topsides facility, underwater part for wave loads, and suitable mooring systems.
  • Moorings consist of components such as anchors, chain cables, and mooring winches.
  • Feedback and control mechanisms like directional positioning systems are essential in mooring systems.
  • Drill ships have moorings that come from a hole called a moonpool, where the drill string comes out.
  • Turret mooring is commonly used in offshore engineering for vessel rotation.
  • The mooring system accounts for approximately 50% of the cost of a floating platform.
  • Marine risers, along with moorings, constitute a significant portion of the platform's cost.

Turn any video into a summary like this

YouTube links, meetings, lectures. With transcripts, search, and chat.

Video description

Elements of Ocean Engineering by Dr. Ashoke Bhar, Department of Ocean Engineering, IIT Kharagpur. For more details on NPTEL visit http://nptel.iitm.ac.in