Huge Scale! I-Beam Manufacturing Process by Melting Metal Scrap. Steel Mass Production Factory
Korea's Steel Production Process
Overview of Pohang Steel Company
- Established in 1954, Pohang Steel is Koreaβs first private steel company, producing various steel products including H-beam section steel used in large structures and civil engineering.
- It ranks as one of the three largest steel companies in Korea and was the 84th largest globally based on production in 2015.
Scrap Metal Collection
- Trucks collect discarded scrap metal nationwide; dust covers are used on city roads but removed inside the factory.
- Approximately 200 trucks deliver around 60,000 tons of scrap metal daily, valued at tens of billions of dollars.
- A massive grapple operates like a claw machine to load different sizes of scrap into a bucket that can hold about 110 tons.
Melting Process
- The electric furnace melts iron scrap at approximately 1600β; workers wear flame-retardant gear due to extreme heat and flames.
- High-voltage current is used to melt the scrap metal while impurities are filtered out with over a 90% recovery rate.
Refining Molten Steel
- Clean molten iron is transferred to a ladle for further processing; it retains a temperature around 1600β during this stage.
- Chemical reactions during subsidiary material input cause sparks; operators visually check the condition before moving to refining.
Casting and Rolling Processes
Casting Molten Iron
- The refined molten steel undergoes two refining processes before being poured into molds through connected nozzles.
- Semi-finished products emerge from molds with surface temperatures between 900~1000β.
Shaping Section Steel
- Gas cutters shape the hot section steel, which is not yet finalized; serial numbers are engraved for identification purposes.
- The semi-finished products are reheated up to 1270Β°C for about two hours before rolling begins.
Finalizing H-Beam Shape
- Softened section steel is pressed multiple times through rolling mills to achieve precise 'H' shapes across ten stands.
- After rolling, water cooling lowers the temperature; coolant is reused after exposure outside.
Final Processing Steps
Cooling and Proofreading
- The cooling process takes about 1 to 2 hours depending on product specifications; remaining coolant evaporates quickly upon contact with air.
Cutting and Binding